What next for costly Mono work?

Chris Caskey, The Union Democrat

PUBLIC MEETING: Sonora City Council, 5 p.m. Monday, City Hall, 94 N. Washington Street

The Sonora City Council will decide Monday whether to award a contract for the Mono Way widening project or throw out the first round of bids after the estimated price came in significantly higher than the $2.75 million engineer's estimate.

The plan is intended to ease traffic between Greenley Road and Fir Drive. Proposed work includes building a retaining wall, replacing a 36-inch culvert and earthwork.

Contractor bids for the work ranged from $3.4 million and $4.6 million.

City Engineer Gerard Fuccillo said his estimate was based on costs seen in previous city projects.

"Admittedly, the city engineer's estimate was optimistic, and with the hope that the bidders would sharpen their pencils in bidding the project," the memo from Fuccillo states.

The process has been complicated by the fact that low bidder KW Emerson requested to withdraw its bid because of a clerical error. And another bidder, George Reed Inc., filed a bid protest alleging the lowest bid was incomplete.

The City Council could accept the low bid as it stands, throw out the low bid or throw out all three and accept a second round under an updated estimate.

"If it is decided to put the project out to rebid, it could be bid in January to preserve next year's schedule," Fuccillo said in his memo.

Timeline estimates had major work beginning in March and wrapping up as early as December 2014.

The plan calls for making the stretch of Mono Way a five-lane thoroughfare to ease traffic. The city is administering the project, but it is a cooperative venture between Sonora and Tuolumne County. The county is covering 90 percent and Sonora is covering 10 percent of the cost through traffic mitigation fees.

The project includes excavation, grading and the construction of new sidewalks along one of the county's busiest roads, which sees 22,000 cars a day. It will also widen a portion of Mountain View Road and add left- and right-turn pockets at Greenley Road and Fir Drive.

Another major component of the project will be a retaining wall that stretches from Roselyn Lane to Fir Drive. The wall's height will range from 12 feet to 4 feet tall, with 16-foot-long panels covering the wall with a material simulating stacked stones.

The city is also considering proposals by local arts groups to create some form of public art along the wall.

The Union Democrat
This image is copyrighted.

Reach all of Sonora, Calaveras County, Tuolumne, Angels Camp, Twain Harte, & Jamestown with your items to sell.

Ads appear Online and in Print

View Classifieds Place an Ad

Connect with The Union Democrat

Union Democrat Newsstand

Wednesday October 26, 2016

Read digital interactive editions of our publications

Read Today's Edition Take A Tour

More Publications by The Union Democrat

View All Publications
Paying the price


Chris Lusardi, of Sonora, is one of thousands of Tuolumne County residents ... more

New oak disease spreads from coast to foothills


A deadly fungus killing oak trees along the coasts of central and ... more

Columbia Elementary board ousts superintendent


Five days after receiving a 2 percent raise, Columbia Union School District ... more

Mudslide knocks out a portion of TUD’s ditch system


The Columbia ditch will be closed until Saturday, following a mudslide that ... more

Battle for cannabis regulation in Calaveras wages on


Strong opinions and loud accusations have made the battle over cannabis cultivation ... more